APCSS Construction Update 
March 18, 2011 - Issue #3

Pile Installation

On March 23rd, three piles will be installed for testing purposes. Work will begin at 9 a.m and end by 5:30 p.m. The piles will be tested in the days following for load bearing capacity. If all tests pass, 28 additional piles will be installed by the end of April.

 

The soil conditions under the site are soft enough that a pile design is important for structural integrity of the building, but the soft soils will allow for minimal noise and vibration during placing of the piles. Each pile should take less than ½ day to install.

 

This test was originally schedule for March 7th and may be rescheduled again if there is inclement weather.

What is this new building?

Wing C  is a new 10,000 square ft. single story building to serve as a state-of-the-art Information Integration Learning Laboratory that includes a 108-person plenary space, six seminar rooms, audio-visual and computer server rooms, required ancillary spaces, and an ethno-botanical garden. Read More

Construction FAQs

 

How long will it take to do all the pile driving to support the new structure?

Testing will be done on Wednesday, March 23rd. Pile driving will occur for several weeks throughout April.  Work will be done from 9 a.m. through 5:30 p.m. to minimize noise impacts to our neighbors.

 

 

How tall will the building be and will it obstruct our views?

The building is a single-story and should not impact anyone's views.

 

There is not enough open space in Waikiki. How much room will this new building take up? 

The current fence line is a construction safety area. The final fence line will only come out as far as absolutely necessary. Once construction is done there will still be ample open green space in the area.  We are also adding an ethno-botanical garden on the Kalakuau side of the campus for the community.

 

Click here to view an animated rendering of the new building.

Contract Information

This military construction project contract is being managed through the U.S. Army Corps of Engineers, Honolulu District. The contractor is Su-mo /Nan JV. 

Is this information useful?

Your feedback is greatly appreciated. Please feel free to let us know if this information is useful to you or if you have questions that you'd like us to answer. You can contact us by replying to this email or call 808-971-8916.

 

Click here to view previous issues this newsletter online:

In this issue:

Pile Installation

What is this new building?

Construction FAQs

Contract Information

Milestones

Contacting APCSS

Thank you for your interest in APCSS activities.

 

If you have any questions or concerns about our projects please feel free to contact Mary Markovinovic via email at pao@apcss.org or call at 808-971-8916 during normal working hours.

 

Also please feel free to recommend that we add someone you know to our distro list.

 

Milestones

 

March - earthwork and test pile driving

 

April - Pile driving beginning Apr. 6. 

 

The building is scheduled be completed in mid-2012.

Web Updates

Follow APCSS On...
Twitter
Facebook
Youtube

APCSS News Archive

Asia-Pacific Center for Security Studies • 2058 Maluhia Rd • Honolulu • HI • 96815
http://www.apcss.org
  Subscribe   ·   Unsubscribe   ·   Preferences   ·   Send to a Friend  
Report Spam
Bookmark and Share