This Saturday, May 7, the construction crew will be on site to work on the water supply lines beginning at 9 a.m. This work must be done on the weekend since it forces a water shut/sprinkler system down at the Center.
The work will involve some localized excavation with a small back hoe, and eight through cuts of 6" steel pipe. New valves will be installed to provide water and fire protection support to the new wing.
We are making every effort to minimize the number of Saturdays worked during this project. Work between 9 a.m. and 6 p.m. is included in the noise permit.
Pile Driving Update
The pile driving went very smoothing. So smoothly that the contractor was able to install them in one day vice four. The next step is putting up the block walls which will begin in mid-May and will take approximately four weeks. |